Author Archives: Phan Tấn Thanh
9566 – Exhaust Stack System
Duration: 11/2023 – 07/2024 Location: Singapore Scope of works: Procurement of raw material, fabricate, packing and...
Long Son Petroleum (LSP)
Duration: 01/2020 – 12/2023 Location: Vung Tau, Vietnam Scope of works: The provision of installation...
Package 1 – Provision of service for the 5th Turnaround of Dung Quat Refinery
Duration: 03/2024 – 04/2024 Location: Quang Ngai, Viet Nam Scope of works: Supplying Maintenance Services...
Completed testing and handover of E-1135 heat exchanger at Dung Quat Refinery.
On the morning of October 9, 2024, Quang Ngai Petroleum Services Joint Stock Company (PTSC...
Complete and Hand Over more than 800 tons of equipment exporting to European market
On July 30, 2024, at Berth No. 1 – PTSC Dung Quat Port, PTSC Quang...
The consortium of PTSC Quang Ngai & PV College Successfully Completed Package 6 – the 5th Turn around project
Package No. 6 – Maintenance Service Contract for Single Point Mooring System (SPM) during the...