EPC PROJECTS
Material tank construction work for the Long Son Petrochemicals Complex
- Scope of work: Material tank construction work for the Long Son Petrochemicals Complex
- Owner: Long Son Petrochemicals Co.,LTD
- Duration: 2025-2027
- Location: Vung Tau, Vietnam
Project on Investment, Repair, and Upgrade of the Sulfur Recovery to Acid System
- Scope of work: Package No. 1 Engineering, Procurement of Materials and Equipment, and Construction (EPC)
- Owner: Ninh Binh Nitrogenous Fertilizer LTD. Company
- Duration: 2025-2026
- Location: Ninh Binh, Vietnam
Construction of an additional crude oil storage tank for the existing Dung Quat Refinery
- Scope of work: Engineering, procurement and construction (EPC) for 01 tank with capacity of 65.000m³
- Owner: Binh Son Refining and Petrochemical Joint Stock Company (BSR).
- Duration: 2025-2026
- Location: Quang Ngai, Vietnam
Component Project No. 3: Airport Essential Facilities – Long Thanh International Airport Construction Project Phase 1
- Scope of work: Package 4.9. EPC of Aircraft Fuel Supply System
- Owner: Airports Corporation of Vietnam - JSC (ACV)
- Duration: 2024 - 2026
- Location: Dong Nai Province, Vietnam
DUNG QUAT BIO-ETHANOL PLANT PROJECT
PROJECT INFORMATION:
- Name: The provision of engineering, procurement and construction for Dung Quat Bio-Ethanol Plant Project
- Scope of work: EPC
- Quantity: 6.000 tons (Steel Structure), 120.000 ID (Pipe)
- Location: Dung Quat Economic Zone, Quang Ngai
- Owner: PetroVietnam Central Bio-Fuel JSC
- Duration: 10/2009 - 2013
TNK-4 PACKAGE – NGHI SON REFINERY
PROJECT INFORMATION:
- Name: The provision of engineering, procurement and construction (EPC) of Tank 4 Package - Nghi Son Refinery & Petrochemical Complex (TNK-4 Package)
- Scope of work: EPC
- Quantity: 6.000 tons (Plate Work), 40 tanks for utilities
- Location: Nghi Son Refinery, Thanh Hoa
- Owner: Nghi Son Refinery & Petrochemical Limited Liability Company
- Duration: 09/2014 - 05/2016
TWO ADDITIONAL CRUDE OIL TANKS & SULFUR PUMPS PROJECT – DUNG QUAT REFINERY
PROJECT INFORMATION:
- Name: The provision of engineering, procurement and construction for Two Additional Crude Oil Tanks & Sulfur Pumps - Dung Quat Refinery
- Scope of work: EPC
- Quantity: 6.500 tons (Steel Structure & Plate Work), 55.000 ID (Pipe)
- Location: Dung Quat Refinery, Quang Ngai
- Owner: Binh Son Refining & Petrochemical Company Limited
- Duration: 10/2009 - 08/2011
P7 WAREHOUSE PROJECT – DUNG QUAT REFINERY
PROJECT INFORMATION:
- Name: The provision of engineering, procurement and construction for P7 additional material storage warehouse project
- Scope of work: EPC
- Quantity: 350 tons (Steel Structure)
- Location: Dung Quat Refinery, Quang Ngai
- Owner: Binh Son Refining & Petrochemical Company Limited
- Duration: 04/2014 - 10/2014
ADDITIONAL SUCTION PUMP LINES FOR EXPORTING PRODUCT A92, DIESEL – DUNG QUAT REFINERY
PROJECT INFORMATION:
- Name: The provision of engineering, procurement and installation for Additional Suction Pump Lines For Exporting Product A92, Diesel Through Truck Loading Dung Quat Refinery
- Scope of work: EPC
- Location: Dung Quat Refinery, Quang Ngai
- Owner: Binh Son Refining & Petrochemical Company Limited
- Duration: 08/2012 - 01/2013