Dự án Bảo dưỡng tổng thể lần 5 – NMLD Dung Quất – Gói thầu số 1
Thời gian: 03/2024 - 04/2024
Địa điểm: Quảng Ngãi, Việt Nam
Phạm vi công việc: Bảo dưỡng sửa chữa Khu vực A2 - Gói thầu số 1
XEM THÊM
Package 7 – Provision of service for the 4th Turn-around of Dung Quat Refinery
PROJECT INFORMATION:
XEM THÊM
- Name: Package 7 - Provision of service for the 4th Turn-around of Dung Quat Refinery
- Scope of work: Maintenance & Repair for SPM (Single Point Mooring)
- Location: Dung Quat, Quang Ngai, Vietnam
- Contractor: Binh Son Refining & Petrochemical Company Limited
- Client/Owner: Binh Son Refining & Petrochemical Company Limited
- Volume of Work: Lump sum basic
- Duration: 08/2020 – 10/2020
Package 4 – Provision of service for the 4th Turn-around of Dung Quat Refinery
PROJECT INFORMATION:
XEM THÊM
- Name: Package 4 - Provision of service for the 4th Turn-around of Dung Quat Refinery
- Scope of work: Maintenance & Repair for Heat Exchangers (H/E and AFC)
- Location: Dung Quat, Quang Ngai, Vietnam
- Contractor: Binh Son Refining & Petrochemical Company Limited
- Client/Owner: Binh Son Refining & Petrochemical Company Limited
- Volume of Work: Lump sum basic
- Duration: 08/2020 – 10/2020
Package 3 – Provision of service for the 4th Turn-around of Dung Quat Refinery
PROJECT INFORMATION:
XEM THÊM
- Name: Package 3 - Provision of service for the 4th Turn-around of Dung Quat Refinery
- Scope of work: Maintenance & Repair for Areas for Utility + Offsite + PP
- Location: Dung Quat, Quang Ngai, Vietnam
- Contractor: Binh Son Refining & Petrochemical Company Limited
- Client/Owner: Binh Son Refining & Petrochemical Company Limited
- Volume of Work: Lump sum basic
- Duration: 08/2020 – 10/2020
Package 2 – Provision of service for the 4th Turn-around of Dung Quat Refinery
PROJECT INFORMATION:
XEM THÊM
- Name: Package 2 - Provision of service for the 4th Turn-around of Dung Quat Refinery
- Scope of work: Maintenance & Repair for Equipment, pipelines of Area A1/A3
- Location: Dung Quat, Quang Ngai, Vietnam
- Contractor: Binh Son Refining & Petrochemical Company Limited
- Client/Owner: Binh Son Refining & Petrochemical Company Limited
- Volume of Work: Lump sum basic
- Duration: 08/2020 – 10/2020
PACKAGE 3 – TURNAROUND 3RD – DUNG QUAT REFINERY
PROJECT INFORMATION:
- Name: Package 3 – Provision of service for the 3rd Turn-around of Dung Quat Refinery for Area A3 and utility, off-site 1, ETP and PP Unit
- Scope of work: Repair & Maintenance
- Quantity: more than 1.000 work items
- Location: Dung Quat Refinery, Quang Ngai
- Owner: Binh Son Refining & Petrochemical Company Limited
- Duration: 06/06/2017 - 06/07/2017
SITE REPAIR WORKS AT MYINGYAN POWER PLANT, MYANMAR (1st & 2nd)
PROJECT INFORMATION:
XEM THÊM
- Name: Repair only bypass side of diverter damper blade optimized for combined cycle operation
- Scope of work: Repair
- Quantity: 2 Units
- Duration: 11/2018 & 10/2019